Green Hydrogen – India’s bet on hydrogen made with renewable power, and whether the numbers add up.

  • $2.1bn National Green Hydrogen Mission (approved outlay)
  • 862,000 t production capacity awarded (across 19 companies)
  • 8,000 t actually commissioned (0.16% of the 2030 target)
  • 100–120 GW of new solar implied (to power 5 MMT a year)

India approved a five-million-tonne green hydrogen target for 2030. Three years in, commissioned capacity stood at roughly 8,000 tonnes a year, or 0.16% of it, with four years left.

The value is not where batteries already work. It is in steelmaking, ammonia, refining, shipping and aviation fuel, which together make up roughly a quarter of global emissions and the hardest quarter to cut. India’s interest is strategic: it imports most of its crude.

SIGHT has awarded about 862,000 tonnes a year across nineteen companies, seventeen percent of the target. Watch the gap between the seventeen percent awarded and the 0.16% actually built.

The signal to watch: Commissioned tonnes, monthly. Awarded is 862,000; built is 8,000.

Where we would take your group

  • An electrolyser manufacturing line. Awarded capacity against installed capacity.
  • A refinery gate. The incumbent building the first refuelling point.
  • A policy economist on the auction. Where the bids cleared, and what they assumed.

Questions for the debrief

  1. Green hydrogen costs roughly twice grey. Early demand had to be allocated to state refiners rather than discovered. When is manufactured demand legitimate industrial policy, and when is it a subsidy trap?
  2. Only ~1% of the mission outlay has been spent, because disbursement is tied to commissioning. Is underspend here a failure or a working control?
  3. Australia, Chile, Morocco and Oman are making the same export pitch. What is India’s defensible advantage? Is it the molecule, or the engineering workforce?